🔐 Two-Factor Authentication
active
SMS provider integration slower than expected

Risk Score

38

Team Members

4

Tasks Complete

8/20(40%)

Target Date

9/21/2025

Velocity Metrics
Team performance across sprints
Average Velocity15 pts
Completed Sprints5
Trendincreasing
Task Progress
Overall completion status
Completion40%

Done

8

In Progress

3

Review

3

Blocked

4

Timeline
Project schedule and progress
Time Elapsed100%
Start Date5/22/2025
Target End9/21/2025
Projected End9/20/2025
Days Remaining193 overdue
Team Capacity
Resource utilization
Utilization121%
Total Capacity140 hrs/week
Active Work169 hrs
Team Members4
High Utilization - Consider Rebalancing